Cost and Duration Optimization at Building C of Dharmais Cancer Hospital Jakarta with TCTO Method Using Primavera P6 Analysis

Authors

  • Sahda Aulia Civil Engineering Study Program, Faculty of Engineering, Sebelas Maret University
  • Setiono Setiono Civil Engineering Study Program, Faculty of Engineering, Sebelas Maret University
  • Muji Rifai Civil Engineering Study Program, Faculty of Engineering, Sebelas Maret University

DOI:

https://doi.org/10.47134/scbmej.v1i4.2722

Keywords:

Optimization, Primavera P6, Time Cost Trade Off

Abstract

In construction projects, cost and duration are important aspects but there are several factors that become obstacles. With these constraints, the project needs to organize its project management to keep it running according to the contract. The method that can be used to manage these obstacles is TCTO (Time Cost Trade Off). There are three scenarios used in this study, namely the addition of working hours, the addition of labors, and the combined (addition of working hours and labors), using the help of Primavera P6. This research aims to analyze the estimated total duration and cost obtained after optimization, compare the total duration and cost obtained before and after optimization, and recommend the most economical alternative among the scenarios carried out. The results of the optimization analysis carried out using additional working hours (scenario 1) are 611 days and an increase in costs; while with additional labors (scenario 2) are 632 days and a decrease in costs; and with combined (scenario 3) are 611 days and a decrease in costs. The most economical alternative from this study is to use scenario 2 because it reduces the duration and cost of the initial cost budget plan of the project.

References

Alaydrus, A. M., & Hardjomuljadi, S. (2018). Desain and buid = analisis faktor keterlambatan proyek Rancang Bangun. Konstruksia, 10(1), 95–116.

Arvianto, R., Sri Handayani, F., & Setiono. (2017). OPTIMASI BIAYA DAN WAKTU DENGAN METODE TIME COST TRADE OFF (TCTO) (Studi Kasus Proyek Bangunan Rawat Inap Kelas III dan Parkir RSUD Dr. Moewardi Surakarta). E-Jurnal MATRIKS TEKNIK SIPIL, 69.

Atmaja, J., & Wijaya, Y. P. (2016). Pengendalian Biaya Dan Waktu Pada Proyek Konstruksi Dengan Konsep Earned Value (Studi Kasus Proyek Pembangunan Jembatan Beringin – Kota Padang). Jurnal Rekayasa Sipil, 13(1), 23–30.

Aulia, M. A., Farisi, A. H., Wibowo, M. A., & Hidayat, A. (2017). Balance Pada Proyek Konstruksi Repetitif ( Studi Kasus : Proyek Pembangunan Apartemen. Analisis Penggunaan Metode Penjadwalan Line of Balance Pada Proyek Konstruksi Repetitif (Studi Kasus : Proyek Pembangunan Apartemen Candiland, 6(1), 211–219.

Aviyani, V., & Dofir, A. (2021). ANALISIS PERCEPATAN PROYEK MENGGUNAKAN METODE TIME COST TRADE OFF DENGAN PENAMBAHAN JAM KERJA DAN TENAGA KERJA Studi Kasus : Pembangunan PKL Higienis Kementerian PUPR. Artesis, 1(2), 125–131. DOI: https://doi.org/10.35814/artesis.v1i2.3217

Budianto, E. A., & Husin, A. E. (2021). Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off pada Proyek Gudang Amunisi. Aplikasi Teknik Sipil, 19(3). https://doi.org/10.55123/storage.v2i3.2344 DOI: https://doi.org/10.12962/j2579-891X.v19i3.9146

Elbeltagi, D. E. (2009). Chapter 3: Project Planning. In Construction Management (pp. 42–73).

Elbeltagi, D. E. (2009). Chapter 7: Time-Cost Trade-Off. In Construction Management (pp. 104–117). https://pecivilexam.com/Study_Documents/Const-Materials-Online/CM-Time-Cost.pdf

Fitrianto, R., & Sumarningsih, D. T. (2016). Penjadwalan Proyek Konstruksi dengan Metode Penjadwalan Precedence Diagram Method (PDM) dan Perhitungan Waktu dengan Program Evaluation and Review Technique (PERT)(Studi Kasus : Proyek Pembangunan Gedung TK Sultan Agung-UII Tahap II, Nglanjaran, Sleman). Universitas Islam Indonesia.

Indonesia, M. T. K. dan T. R. (2014). Peraturan Menteri Tenaga Kerja dan Transmigrasi Republik Indonesia Nomor 4 Tahun 2014.

M. Priyo, S. A. (2016). Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off : Studi Kasus Proyek Pembangunan Prasarana Pengendali Banjir. Semesta Teknika, 19(1), 1–15. https://journal.umy.ac.id/index.php/st/article/view/2233 DOI: https://doi.org/10.18196/st.v18i1.703

Mahapatni, I. A. P. S. (2019). Metode Perencanaan dan Pengendalian Proyek Konstruksi. In UNHI Press.

Menteri Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia. (2022). Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Budang Pekerjaan Umum dan Perumahan Rakyat.

Muharani, A., Mulyatno, I. P., & Jokosisworo, S. (2020). Optimasi Percepatan Proyek Pembangunan Kapal Kelas I Kenavigasian dengan Metode Pendekatan Analisa Time Cost Trade Off. Jurnal Teknik …, 8(3), 330–338. https://ejournal3.undip.ac.id/index.php/naval/article/view/27228

Pankaj, V., Pitroda, J., & Bhavsar, A. N. (2020). Effective Scheduling and Control of Construction Project Using Primavera P6 : A Review. UGC Care Journal, 40(50).

Prajoko, A., & Manurung, E. (2018). Analisis penjadwalan proyek konstruksi menggunakan simulasi monte carlo (studi kasus pembangunan gedung di Bintaro, Jakarta. Seminar Nasional Cendekiawan Ke 4 Tahun 2018, 4(1), 27–32.

Pratiwi, R., Mulia Devi, S., Marini, A., & Maya Sari, H. (2022). Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Tcto) Pada Proyek Penambahan Bangunan Pasar Rakyat. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 4(2), 93–105. https://doi.org/10.36277/transukma.v4i2.134 DOI: https://doi.org/10.36277/transukma.v4i2.134

PROSEDUR PENYESUAIAN HARGA SOP/UPM/DJBM-116. (2017).

Rahayu, S., Nurwan, & Wungguli, D. (2022). Analisis Critical Path Method dan Time Cost Trade Off dalam Optimasi Waktu dan Biaya Pengerjaan Proyek Pembangunan Rumah Sakit. Jurnal Ilmiah Matematika Dan Terapan, 19(2), 227–242. https://doi.org/10.22487/2540766x.2022.v19.i2.16176 DOI: https://doi.org/10.22487/2540766X.2022.v19.i2.16176

Rahmawan, S. A., Abidin, Z., Wibowo, K., & Adhy, D. S. (2020). Analisa Manajemen Biaya dan Waktu pada Proyek Gedung Kantor Pusat dan Kantor Pusat Operasional PT . Lkm Demak Sejahtera. Konfrensi Ilmiah Mahasiswa UNISSULA (KIMU), 4(Kimu 4), 268–276.

Republik Indonesia, P. (2021). Peraturan Pemerintah Nomor 35 Tahun 2021 Tentang Perjanjian Kerja Waktu Tertentu, Alih Daya, Waktu Kerja dan Waktu Istirahat, dan Pemutusan Hubungan Kerja [Government Regulation Number 35 of 2021 concerning Work Agreements for Certain Time, Outsourcing, W. Peraturan Pemerintah Republik Indonesia Nomor 35 Tahun 2021, 086142, 42. https://peraturan.bpk.go.id/Home/Details/161904/pp-no-35-tahun-2021

Reynaldi, C., & Sutandi, A. (2022). Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off - Studi Kasus Apartemen Collins Boulevard. JMTS: Jurnal Mitra Teknik Sipil, 5(2), 497–506. https://doi.org/10.24912/jmts.v5i2.16450 DOI: https://doi.org/10.24912/jmts.v5i2.16450

Setiono, S., Suryoto, S., & Supriyor, D. Q. (2022). Analisis Optimasi Biaya dan Waktu Proyek dengan Metode Time Cost Trade Off Menggunakan Aplikasi Primavera P6 (Studi Kasus Proyek Penataan Koridor Jl. Ir. Juanda, Surakarta). Matriks Teknik Sipil, 10(2), 90. https://doi.org/10.20961/mateksi.v10i2.56376 DOI: https://doi.org/10.20961/mateksi.v10i2.56376

Shah, P., & Chandragade, A. A. (2023). Application of project management tool in construction for Planning, Scheduling and Optimization. Materials Today: Proceedings, 77, 773–779. https://doi.org/10.1016/j.matpr.2022.11.446 DOI: https://doi.org/10.1016/j.matpr.2022.11.446

Simorangkir, S. P., Sihombing, A. T., Anderson, F., & Ginting, J. A. R. (2020). ANALISA JARINGAN KERJA DAN PENENTUAN JALUR KRITIS DENGAN CRITICAL PATH METHODE (CPM) STUDI KASUS PEMBANGUNAN GEDUNG KEJAKSAAN NEGERI KABUPATEN BATUBARA. September, 932–937.

Sulistyo, A. B., & Al Fikri, M. (2021). Analisis Optimalisasi Waktu Dan Biaya Proyek Konstruksi Menggunakan Metode Time Cost Trade Off (Studi Kasus: Proyek Pembangunan Jalan Gorda-Bandung). Jurnal InTent, 4(1), 25–40.

Downloads

Published

2024-06-14

How to Cite

Aulia, S., Setiono, S., & Rifai, M. (2024). Cost and Duration Optimization at Building C of Dharmais Cancer Hospital Jakarta with TCTO Method Using Primavera P6 Analysis. Sustainable Civil Building Management and Engineering Journal, 1(4), 13. https://doi.org/10.47134/scbmej.v1i4.2722