Value Engineering Analysis on Building Structure (Case Study: Java Steam Power Plant 9&10 2x1000 MW Suralaya Project)

Authors

  • Reza Andhika Putra Sebelas Maret University
  • Setiono Setiono Sebelas Maret University
  • Fajar Sri Handayani Sebelas Maret University

DOI:

https://doi.org/10.47134/scbmej.v1i3.2835

Keywords:

Cost, Precast Concrete, Value Engineering

Abstract

Cost is an important element in the success of a project because problems with project implementation costs can hinder the achievement of the project. Problems in project implementation related to costs can be overcome by carrying out value engineering analysis. The concept of value engineering is a systematic effort to analyze existing problems and aims to achieve the desired functions or types of work with efficient costs and optimal results. The value engineering carried out in the case study analyzed by the author is a change in the implementation of concrete work from conventional methods to precast methods to obtain cost efficiency. The method used is a data collection method and analysis method according to the value engineering analysis stages. The results of the value engineering analysis obtained by the author through creative ideas in the form of changing conventional concrete work to precast concrete are savings in work costs on building structural components in the form of slabs. The cost savings obtained were Rp695,905,059.00 or 2.21%.

References

Albar, R. F. (2023). Evaluasi Kinerja Manajemen Konstruksi Proyek Pembangunan Kantor Dinas Kesehatan. Jurnal Konstruksi Institut Teknologi Garut, 21(2). https://doi.org/10.33364/konstruksi/v.21-2.1409. DOI: https://doi.org/10.33364/konstruksi/v.21-2.1409

Alkalis, G. (2021, September 28). PLTU Jawa 9 dan 10 Pembangkit Ramah Lingkungan Perkuat Kelistrikan Jamali. Ruang Energi. Diakses pada 8 September 2023, dari https://www.ruangenergi.com/pltu-jawa-9-dan-10-pembangkit-ramah-lingkungan-perkuat-kelistrikan-jamali/.

Badan Standarisasi Nasional. (2019). Persyaratan Beton Struktural Untuk Bangunan Gedung (SNI No. 2847-2019).

Cahyaningsih, S., Wulan, D. R., & Sembiring, T. (2019). Water quality assessment around a coal-fired power plant in southern coast of Java, Indonesia. Regional Studies in Marine …. https://www.sciencedirect.com/science/article/pii/S2352485518302159

Darmawan, N., & Yuwono, T. (n.d.). The Effect of Jakarta Bay Reclamation on the Performance of the Steam Turbine of Muara Tawar Power Plant, Indonesia. Researchgate.Net. https://www.researchgate.net/profile/Triyogi-Yuwono/publication/335579643_Effect_of_Increasing_Sea_Water_Temperature_on_Performance_of_Steam_Turbine_of_Muara_Tawar_Power_Plant/links/5e768b744585157b9a5130fb/Effect-of-Increasing-Sea-Water-Temperature-on-Performance-of-Steam-Turbine-of-Muara-Tawar-Power-Plant.pdf

Devi, O., & Putu, D. K. (2020). Improving Overhaul Process on Steam Power Plants using Lean Thinking and LCA. IOP Conference Series: Earth and …. https://doi.org/10.1088/1755-1315/448/1/012043 DOI: https://doi.org/10.1088/1755-1315/448/1/012043

Dimyati, H., & Nurjaman, K. (2004). Manajemen Proyek. Bandung: Pustaka Setia. Vol.12 (2), ISBN: 978-979-076-438-5.

Fitriyana, T. (2019). Analisis Manajemen Konstruksi Pembangunan Gedung POLRESTA Pontianak Dengan Perhitungan SNI dan Analisa Software Microsoft Project 2016. Jurnal Teknik Kelautan, PWK, Sipil, dan Tambang Universitas Tanjungpura, 6(3). https://dx.doi.org/10.26418/jelast.v6i3.38844.

Gulo, D. P. J. (2022). Analisa Manajemen Konstruksi Proyek Pembangunan Gedung Koperasi Astra Internasional Jakarta Pusat. Jurnal Ilmiah Teknik Sipil Universitas Darma Agung Medan, 11(1). http://dx.doi.org/10.46930/tekniksipil.v11i1.1720. DOI: https://doi.org/10.46930/tekniksipil.v11i1.1720

Hendrianto, G. K. (2018). Analisis Value Engineering untuk Efisiensi Biaya (Studi Kasus: Proyek Apartemen Yukata Suites Alam Sutera Tangerang). Matriks Teknik Sipil, 6(4). https://doi.org/10.20961/mateksi.v6i4.36538. DOI: https://doi.org/10.20961/mateksi.v6i4.36538

Hutauruk, B. C., Martono, D. N., & ... (2021). Risk and Impact Control of PM2. 5 and SO2 Exposure of Power Plant to Communities (A Case Study in the Steam Power Plant Babelan Bekasi). Jurnal Kesehatan …. https://pdfs.semanticscholar.org/15fb/f30055fc20a578ccb6c39c6bc28df7dbeb9e.pdf

Jason, A., Asih, A. M. S., & Yuniarto, H. A. (2019). Analysis of coal allocation on steam power plants and the effect of multi-suppliers, demand and time variations on coal’s safety stock. IOP Conference Series …. https://doi.org/10.1088/1757-899X/673/1/012074 DOI: https://doi.org/10.1088/1757-899X/673/1/012074

Komarudin, K., Abrianto, H. H., Multi, A., & ... (2023). Performance analysis of extraction condensing turbine-unit 1 at Pltu X, Bekasi, West Java. International Journal of …. https://greenpub.org/IJAM/article/view/217 DOI: https://doi.org/10.38035/ijam.v2i1.217

Lukmana, A. H., & Helmy, M. F. (2020). A Techno-Economic Analysis of Geothermal Energy in West Java. … of LPPM UPN …. http://proceeding.researchsynergypress.com/index.php/ess/article/view/130

Mozes, M. S. (2017). Kuat Lentur Panel Lantai Pracetak Beton Ringan Menggunakan Agregat Kasar Pumice. Laporan Tugas Akhir, Yogyakarta

.

Musliha, S. S. A. (2021). Analisis Value Engineering pada Struktur Bangunan dengan Metode Analytical Process (AHP) (Studi Kasus: Proyek Supporting Unit DPRD Kota Salatiga). Matriks Teknik Sipil, 9(1).

https://doi.org/10.20961/mateksi.v9i1.51241. DOI: https://doi.org/10.20961/mateksi.v9i1.51241

Muslihudin, M., Adawiyah, W. R., Hendarto, E., & ... (2022). Environmental constraints in building process a sustainable geothermal power plant on the slopes of slamet mount, central java, indonesia. catalog.lib.kyushu-u.ac.jp. https://catalog.lib.kyushu-u.ac.jp/ja/recordID/4793669/?repository=yes DOI: https://doi.org/10.5109/4793669

Muslim-Muslim, M., Wulandari, S. Y., Maslukah, L., & ... (2024). Radiological impact of the operation of two Steam Power Plants on the activity levels of 232Th, 226Ra and 40K in the sediments at Semarang and Cirebon, Indonesia. researchsquare.com. https://www.researchsquare.com/article/rs-4480254/latest DOI: https://doi.org/10.21203/rs.3.rs-4480254/v1

Nugraha, A. D., & Muflikhun, M. A. (2023). Failure in power plant system related to mitigations and economic analysis; A study case from steam power plant in Suralaya, Indonesia. Results in Engineering. https://www.sciencedirect.com/science/article/pii/S2590123023001317 DOI: https://doi.org/10.1016/j.rineng.2023.101004

Prabasiwi, D. S., Murniasih, S., & ... (2020). Transfer factor as indicator of heavy metal content in plants around adipala steam power plant. Journal of Physics …. https://doi.org/10.1088/1742-6596/1436/1/012133 DOI: https://doi.org/10.1088/1742-6596/1436/1/012133

Prabasiwi, D. S., Sukirno, S., & Murniasih, S. (2020). Assessment of heavy metals pollution and risks around Tuban steam power plant using neutron activation analysis. AIP Conference Proceedings. https://doi.org/10.1063/5.0000931/14209714/030005_1_online DOI: https://doi.org/10.1063/5.0000931

Prasetyo, B. T., Oktaufik, M. A. M., & ... (2019). Testing of Early Stage of BPPT-3MW Condensing Type Small Scale Geothermal Power Plant–Kamojang-Indonesia. Journal of Physics …. https://doi.org/10.1088/1742-6596/1376/1/012014 DOI: https://doi.org/10.1088/1742-6596/1376/1/012014

Prasetyo, B. T., Oktaufik, M. A. M., & Himawan, S. (2019). Design, construction and preliminary test operation of bppt-3mw condensing turbine geothermal power plant. catalog.lib.kyushu-u.ac.jp. https://catalog.lib.kyushu-u.ac.jp/ja/recordID/2321012/?repository=yes DOI: https://doi.org/10.5109/2321012

Purnomo, D. S., & Haryono, T. (2020). Derating Prediction Due to Scaling at Kamojang Geothermal Turbine Using Nozzle Blocking Ratio Calculation. … in Energy and Electric Power (ICT …. https://ieeexplore.ieee.org/abstract/document/9249825/ DOI: https://doi.org/10.1109/ICT-PEP50916.2020.9249825

Rani, H. A. (2022). Konsep Value Engineering Dalam Manajemen Proyek Konstruksi. Yogyakarta: Deepublish Publisher.

Rosyid, H. A. (2021). Exergy analysis of renewable energy power plant with organic rankine cycle for regions outside Java Island. IOP Conference Series: Earth and Environmental …. https://doi.org/10.1088/1755-1315/700/1/012027 DOI: https://doi.org/10.1088/1755-1315/700/1/012027

Rudiyantoa, B., Wicaksonob, A., & ... (2023). Evaluation and Optimization Based on Exergy in Kamojang Geothermal Power Plant Unit 3. International Journal on …. https://www.researchgate.net/profile/Bayu-Rudiyanto/publication/377389018_Evaluation_and_Optimization_Based_on_Exergy_in_Kamojang_Geothermal_Power_Plant_Unit_3/links/662b088435243041534b8f44/Evaluation-and-Optimization-Based-on-Exergy-in-Kamojang-Geothermal-Power-Plant-Unit-3.pdf

Sagaf, M. (2020). Predicting Boiler Efficiency Deterioration using Energy Balance Method: Case Study in 660 Mw Power Plant Jepara, Central Java, Indonesia. Journal of Thermal Engineering. https://dergipark.org.tr/en/pub/thermal/article/821052 DOI: https://doi.org/10.18186/thermal.821052

Santoso, V. Y. (2020). Penerapan Value Engineering pada Struktur Bangunan Gedung (Studi Kasus: Proyek Gedung Kantor Dinas Pemadam Kebakaran Kota Surakarta). Matriks Teknik Sipil, 8(2). https://doi.org/10.20961/mateksi.v8i2.44175.

Sufyana, C. M., Akbar, F. T., & Srigutomo, W. (2023). … and simulation of a single-flash geothermal power plant involving non-condensable gas: a case study of Kamojang geothermal field in Garut, West Java …. Geothermal Energy. https://doi.org/10.1186/s40517-023-00249-3 DOI: https://doi.org/10.21203/rs.3.rs-1977026/v1

Syahputra, R., Nugroho, A. W., & ... (2019). Dynamic Performance of Synchronous Generator in Steam Power Plant. International …. https://pdfs.semanticscholar.org/7f02/af6e85832a8fc1bfd65aab884ccf83511ef2.pdf DOI: https://doi.org/10.14569/IJACSA.2019.0101251

Tama, A. K. (2020). Analisis Kinerja Manajemen Konstruksi Pada Proyek Gedung Digitasi Universitas Negeri Semarang. Jurnal Teknik Sipil Universitas Negeri Semarang.

Triani, M., Nurfanani, A., Aditya, I. A., & ... (2024). Mapping analysis of biomass potential on Java Island for supporting power plant: A review. E3S Web of …. https://www.e3s-conferences.org/articles/e3sconf/abs/2024/49/e3sconf_talenta2024_02012/e3sconf_talenta2024_02012.html DOI: https://doi.org/10.1051/e3sconf/202451902012

Triwiyono, A. (2005). Bahan Ajar Struktur Beton Pracetak. Yogyakarta: Jurusan Teknik Sipil Universitas Gadjah Mada.

Wibowo, P. (2020). Analisis Manajemen Konstruksi Pembangunan Gedung Rawat Inap Kelas III RSUD Waled Kabupaten Cirebon. Jurnal Konstruksi UNSWAGATI CIREBON, 9(2). https://dx.doi.org/10.33603/jki.v9i2.3928.

Wulandari, A. (2022). Analisis Value Engineering Dengan Penggantian Bahan Additive Campuran Semen pada Struktur Beton (Studi Kasus: Gedung Graha Bakti Budaya Proses Revitalisasi PKJ TIM Tahap II). Matriks Teknik Sipil, 10(4). https://doi.org/10.20961/mateksi.v10i4.61565. DOI: https://doi.org/10.20961/mateksi.v10i4.61565

Yudisaputro, H., Caesarendra, W., & ... (2021). A study on the performance and reliability effect of low-rank coal to the steam power plant. Journal of Physics …. https://doi.org/10.1088/1742-6596/1845/1/012053 DOI: https://doi.org/10.1088/1742-6596/1845/1/012053

Downloads

Published

2024-07-04

How to Cite

Putra, R. A., Setiono, S., & Fajar Sri Handayani. (2024). Value Engineering Analysis on Building Structure (Case Study: Java Steam Power Plant 9&10 2x1000 MW Suralaya Project). Sustainable Civil Building Management and Engineering Journal, 1(3), 11. https://doi.org/10.47134/scbmej.v1i3.2835

Issue

Section

Articles

Most read articles by the same author(s)

1 2 > >> 

Similar Articles

1 2 3 4 > >> 

You may also start an advanced similarity search for this article.