A Comparative Analysis of the CPM and PERT Methods in Project Time Management for a High-Rise Building Construction Project in Yogyakarta

Authors

  • Fazabella Wijaya Santoso Universitas Sebelas Maret
  • Fajar Sri Handayani Universitas Sebelas Maret
  • Setiono Universitas Sebelas Maret

DOI:

https://doi.org/10.47134/scbmej.v2i2.3927

Keywords:

CPM, PERT, Scheduling, Construction Management

Abstract

This study examines the comparison of PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) in time management for construction projects through a case study of a 21-story high-rise building project in Yogyakarta. The research is motivated by the need for effective time management in construction projects to avoid delays that may escalate costs and disrupt project execution. The objectives are to determine the estimated duration for completing the building’s structural work, compare the differences between the initial schedule and the results of PERT and CPM analyses. The study employs a case study approach, with primary data collected through direct interviews with project stakeholders regarding activity durations and predecessors, as well as secondary data from project documentation, including schedules and structural drawings. Data analysis involves applying PERT calculations using three-time estimates (optimistic, most likely, and pessimistic) and identifying critical paths through CPM. Data processing and network diagram visualization are conducted using a project management software to comprehensively map critical and non-critical project activities.  Results indicate that the CPM method predicts a project duration of 419 days, 237 days shorter than the initial schedule, while the PERT method estimates 580 days, 76 days shorter than the original timeline, with an 82.98% probability of timely completion.  

References

Akila, S. (2023). A STUDY ON DIFFERENCE BETWEEN CPM AND PERT. International Journal of Creative Research Thoughts (IJCRT), 11(5), 2320–2882. ijcrt.org

Ardany, R., Abdurrahman, & Cahyadi, H. (2022). Evaluasi Waktu Pekerjaan Dengan Menggunakan Metode PERT Pada Proyek Peningkatan Saluran Irigasi Bandara Syamsudin Noor. Universitas Islam Kalimantan Muhammad Arsyad Al Banjari.

Bagshaw, K. B. (2021). PERT and CPM in Project Management with Practical Examples. American Journal of Operations Research, 11(04), 215–226. https://doi.org/10.4236/ajor.2021.114013

Belferik, R., Andiyan, A., Zulkarnain, I., Munizu, M., Samosir, J. M., Afriyadi, H., Rusmiatmoko, D., Adhicandra, I., Syamil, A., Ichsan, M., & Prasetyo, A. (2023). Manajemen Proyek (Teori & Penerapannya) (Efitra & Sepriano, Eds.; 1st ed.). PT. Sonpedia Publishing Indonesia.

Hanifazaki, N. (2023). Dari Perencanaan hingga Kinerja: Analisis Komprehensif Realisasi Biaya Proyek (Artikel Calon Pegawai Organik (CPO) Management Trainee).

Iriyanto, S. M., & Yommy, S. Y. O. (2017). ANALISA PERENCANAAN WAKTU DENGAN METODE PERT PADA PELAKSANAAN PROYEK PEMBANGUNAN GEDUNG NEGARA PROVINSI PAPUA. Jurnal Portal Sipil, 6(2), 10–28. https://ojs.ustj.ac.id/sipil/article/view/217

Mahyuddin, Ritnawati, Rachim, F., Mursalim, E., Pandarangga, A. P., Sidiq, Y., & Rosytha, A. (2023). Manajemen Proyek Konstruksi (A. Karim, Ed.; 1st ed.). Yayasan Kita Menulis.

Megawati, L. A., & Lirawati. (2021). ANALISIS FAKTOR KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN GEDUNG. Jurnal Teknik: Majalah Ilmiah Fakultas Teknik UNPAK, 21(2), 27–34. https://doi.org/10.33751/teknik.v21i2.3282

Nemaa, Z. K., & Aswed, G. K. (2021). Forecasting construction time for road projects and infrastructure using the fuzzy PERT method. IOP Conference Series: Materials Science and Engineering, 1076(1), 012123. https://doi.org/10.1088/1757-899X/1076/1/012123

Nugraha, A. D., & Waskito, J. P. H. (2023). EVALUASI PELAKSANAAN PROYEK DENGAN METODE CPM DAN PERT (STUDI KASUS PROYEK PEKERJAAN FINISHING LANJUTAN PEMBANGUNAN GEDUNG PROGRAM STUDI DESAIN INTERIOR TAHUN 2019 KAMPUS ITS). Axial: Jurnal Rekayasa Dan Manajemen Konstruksi, 11(2), 79–90. https://doi.org/10.30742/axial.v11i3.3258

Oktafiana, L., & Baroroh, I. (2022). Comparative Analysis of CPM, PDM and PERT Methods in Ship Repair Scheduling Planning KN. RB 309 Ternate 01. BERKALA SAINSTEK, 10(3), 162. https://doi.org/10.19184/bst.v10i3.32479

Pontan, D. (2024). MANAJEMEN PROYEK KONSTRUKSI: Konsep, Strategi, dan Praktik Dalam Teknik Sipil (M. Mirsal, Ed.; 1st ed.). PT Media Penerbit Indonesia.

Putra, P. (2025). Pengendalian Waktu Pekerjaan Konstruksi Pembangunan RSUD Dr. Sobirin Kabupaten Musi Rawas. LITERA: Jurnal Ilmiah Multidisiplin, 2(1), 154–168. https://litera-academica.com/ojs/litera/

Santosa, B. (2009). Manajemen Proyek: Konsep & Implementasi (1st ed.). Graha Ilmu.

Saputro, A. F., & Aufa, B. A. (2024). PENERAPAN KONSEP BUILDING INFORMATION MODELING (BIM) DALAM PERENCANAAN ESTIMASI BIAYA DAN PERCEPATAN PENJADWALAN PADA PEKERJAAN STRUKTUR (Studi Kasus Proyek Pembangunan Gedung Asrama Terpadu MAN 2 Kudus). Universitas Islam Sultan Agung Semarang.

Setiawati, S., Syahrizal, & Dewi, R. (2016). Penerapan Metode CPM Dan PERT Pada Penjadwalan Proyek Konstruksi (Studi Kasus: Rehabilitasi / Perbaikan Dan Peningkatan Infrastruktur Irigasi Daerah Lintas Kabupaten/Kota D.I Pekan Dolok). Department of Civil Engineering Undergraduate Paper USU-IR, 6(1), Art. 1. https://repositori.usu.ac.id/handle/123456789/80694

Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) (2nd ed., Vol. 1). ERLANGGA.

Toricelli, M., & Budiyanto, V. (2021). ANALISIS RISIKO RANTAI PASOK BAJA TULANGAN DAN BETON READY MIX PADA PROYEK KONSTRUKSI GEDUNG DALAM MASA PANDEMI COVID-19 [Universitas Katolik Soegijapranata]. https://repository.unika.ac.id/id/eprint/24475

Tuanaya, A. H., Yan, V., Ilwaru, I., & Lesnussa, Y. A. (2024). Optimization of Flat Construction Implementation Time Using Critical Path Method and Project Evaluation and Review Technique. Pattimura International Journal of Mathematics, 3(2). https://doi.org/10.51135/pijmathvol3iss2p39-50

Widiasanti, I., & Lenggogeni. (2013). Manajemen Konstruksi (P. Latifah, Ed.; 1st ed.). PT REMAJA ROSDAKARYA.

Downloads

Published

2025-05-01

How to Cite

Santoso, F. W., Handayani, F. S., & Setiono. (2025). A Comparative Analysis of the CPM and PERT Methods in Project Time Management for a High-Rise Building Construction Project in Yogyakarta. Sustainable Civil Building Management and Engineering Journal, 2(2), 13. https://doi.org/10.47134/scbmej.v2i2.3927